Agitator scale-up calculator (pilot to plant)

Take an agitator that works in the lab or pilot plant and find the plant speed and power for a geometrically similar reactor. Compare the five common scale-up rules side by side.

Plant rpmkWAll rules compared

1. Pilot or lab vessel

mm
mm
litres
rpm

2. Plant vessel and liquid

mm
kg/m³
cP

Plant speed N₂

85rpm

Constant power per volume (P/V)

Plant shaft power

1.23kW

0.198 kW/m³

Motor

2.2kW

Impeller D₂ 800 mm

Geometrically similar scale-up
Scale ratio L = T₂/T₁6.67
Plant impeller diameter D₂800 mm
Plant working volume6.222 m³ (6,222 L)
Pilot power and P/V4.17 W, 0.198 kW/m³
Pilot tip speed and Re1.88 m/s, Re 7,560
Plant Reynolds number94,856

All scale-up rules compared

BasisrpmkWkW/m³Tip m/sReBlend time × pilot
Constant power per volume (P/V)851.230.1983.5594,8563.5
Constant tip speed (torque per volume)450.1840.02961.8850,4006.7
Constant solids suspension (Njs)600.4330.06962.5166,9915
Constant blend time30054.68.7812.573,36,0001
Constant Reynolds number6.70.0006250.00010.287,56044.4
Use this basis for: Most turbulent duties: mass transfer, gas dispersion, liquid-liquid.
The Reynolds number is 7,560 at one of the scales, below fully turbulent. Power numbers and blend times change between scales; check the regime before relying on P/V.

Want these numbers checked?

Send them to a SEMCO process engineer for a free review, sizing and budget price.

Discuss on WhatsApp

How this calculator works

In geometric scale-up every dimension grows by the same ratio L = T₂/T₁: impeller diameter, liquid height and clearances. The volume grows by L³.

What you hold constant decides the plant speed. Constant power per volume (N ∝ L^-2/3) suits most turbulent duties. Constant tip speed (N ∝ L^-1) keeps the maximum shear the same. Constant Njs (N ∝ L^-0.85) keeps solids suspended. Constant blend time keeps N the same and is usually too expensive. Constant Reynolds number (N ∝ L^-2) is only used in laminar processes.

Power at each scale uses the impeller's power number, including the laminar term, so the tool stays correct when the pilot runs in the transitional regime.

Formulas used

Scale-up speed

N2=N1(T1T2)x

x = 2/3 for constant P/V, 1 for tip speed, 0.85 for Njs, 0 for blend time, 2 for Reynolds number.

Power

P=Np ρ N3D5, Np=Np,turb+KpRe

Assumptions and limits

  • Geometrically similar vessels and impellers, with the same number of impellers and baffles.
  • Same liquid at both scales. If the plant runs hotter or with more solids, change the inputs to suit.
  • Heat transfer does not scale with the agitator alone: jacket area per volume falls as 1/L, so check the batch heating time separately.

Worked example

A 300 mm pilot vessel with a 120 mm pitched blade turbine at 300 rpm, scaled to a 2 m reactor at constant P/V.

  1. L = 2,000 ÷ 300 = 6.67. Plant impeller D₂ = 120 × 6.67 = 800 mm, volume grows 296 times.
  2. N₂ = 300 × 6.67^(-2/3) ≈ 85 rpm, drawing about 1.2 kW at 0.2 kW/m³, the same P/V as the pilot.
  3. Constant tip speed would give 45 rpm and less power; constant blend time would need 300 rpm and hundreds of times more power, which is why it is rarely used.

Frequently asked questions

Which scale-up rule should I use?

Constant power per volume for most turbulent processes such as reactions with mass transfer, gas dispersion and liquid-liquid dispersion. Constant tip speed for shear-sensitive products. The Njs rule for solids suspension.

Why does blend time get longer in a bigger reactor?

At constant P/V, speed falls as the vessel gets bigger, and turbulent blend time is inversely proportional to speed. A plant reactor typically blends two to four times slower than the pilot vessel.

What if my plant reactor is not geometrically similar?

Use the agitator design and comparison tool with the plant vessel's real dimensions and the pilot's P/V or tip speed as the target.

Need it designed and built?

SEMCO designs, fabricates and commissions evaporators, ZLD plants, heat exchangers, reactors and vacuum systems in its own factories in Pune and Solapur.

Results are engineering estimates for early sizing and budgeting. Final designs depend on your liquid, site and codes, and are confirmed in SEMCO's proposal. Method reviewed by Jogender Dhayal, Director, SEMCO.